Public Works Committee


Print

Return to the Search Page Return to the Agenda
  6.1.       
Meeting Date: 09/21/2021  
By: Bruce Westby, Engineering/Public Works

Title:
Receive Staff Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
  • Wetland 114P Outlet Control Improvements (#19-07)
    • Work requested by Minnesota DNR
    • Construction proposed for 2022
  • Variolite Street Reconstruction (#20-01)
    • Final payment September 2021
  • Riverdale Drive Reconstruction – Feldspar St. to Sunfish Lake Blvd. (#21-00)
    • Construction substantially complete
    • Final payment 2022
  • 2022 PMP project updates
  • Tiger Street Reconstruction (#21-02)
    • Construction substantially complete
    • Final payment 2022  
  • Business Park 95 Street Reconstructions (#21-03)
    • Construction substantially complete
    • Final payment 2022  
  • 2021 Neighborhood Pavement Overlay Improvements (#21-04)
    • Construction substantially complete
    • Final payment 2021/22
  • 2021 MSA Pavement Overlay Improvements (#21-05)
    • Construction substantially complete
    • Final payment 2021/22
  • 2021 Crack Seal Improvements (#21-06)
    • Construction complete
    • Final payment 2021
  • 2021 WTP Trunk Watermain Improvements (#21-08)
    • Plans complete (SEH, Inc.)
    • Construction originally proposed for summer/fall 2021
    • SEH recommends fall 2021 bids, spring 2022 construction
    • CC to consider authorizing Ads for Bids October 26, 2021
  • 2021 Water Treatment Plant (#21-09)
    • Contract execution in progress
    • Design proposed 2021/22
    • Construction proposed 2022/23
  • 2021 Additional Pavement Overlay Improvements (#21-12)
    • Construction in progress
 
Anoka County Improvement Projects
  • Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive
    • Anoka County received $1.35M in HSIP funds (est. project cost = $1.5M)
    • Anoka County and City of Ramsey share is $150,000 each (per $1.5M est.)
    • Construction proposed for 2023, pending City & County approvals
    • Anoka County presented project at July 27 City Council work session
    • Anoka County is preparing preliminary plans
  • CSAH 116 Interim Improvements
    • Adding right turn lane on Sunwood Dr west of Bunker Lk Blvd
    • Forest Lake Contracting awarded contract
    • Construction in progress
  • CSAH 116 & TH 47 Intersection Improvements
    • Construction completion anticipated fall 2021
 
MnDOT Improvement Projects
  • US 10 / 169 & Ferry Street / TH 47 Interchange
    • Construction proposed 2022 – 2023
  • Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
    • Preliminary design on hold
    • MnDOT exploring realignment of Highway 47 to remove S-curve
    • Tentatively proposed for construction in 2024 or later – Update attached
  • Rum River Bridge Replacement
    • Construction proposed 2022 – 2023
    • Proposing three lanes between Highway 47 and 7th Street
 
Studies & Items of Interest
  • 5805 148th Lane NW
    • Meeting with property owner 9 AM on Wednesday, 9/22
    • More detailed update to be presented at October 19 PWC meeting
  • Anoka Solution Highway 10 Improvements
    • Construction proposed 2022 – 2023
  • Ramsey Gateway Highway 10 Improvements
    • Preliminary design in progress
    • Fully funded
  • NW Metro Mississippi River Crossing Feasibility Analysis
    • Updates to be presented in September
  • Reduced Speed Limits on Local Streets
    • No new requests received since last discussed
    • Staff continues to monitor actions in other cities   
Timeframe:
Staff estimates up to 10 minutes will be needed for updates and discussion.  
Observations/Alternatives:
NA
Funding Source:
NA
Recommendation:
NA
Action:
No formal action required.  For Committee review and discussion purposes only.  

Attachments
Hwy 47 and BNSF RR Crossing update

<
Form Review
Inbox Reviewed By Date
Grant Riemer Grant Riemer 09/16/2021 01:50 PM
Kurt Ulrich Kurt Ulrich 09/16/2021 02:41 PM
Form Started By: Bruce Westby Started On: 09/16/2021 11:45 AM
Final Approval Date: 09/16/2021

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2022 Destiny Software Inc. All Rights Reserved.